Water law authorisation - service water wells

If you want to use groundwater for industrial water purposes, you need a permit under water law.

Course description

The construction of a service water well must be notified to the Munich Water Management Office at least one month in advance using the form "Bohranzeige Brunnen" (drilling notification for wells) found under "Documents and links".

In addition to the notification, a permit under water law is required for the extraction of groundwater. This must be applied for in good time before the planned start.

Required documents

See information sheet "Application documents for groundwater abstraction for industrial water purposes" from the Munich Water Management Office (available under "Documents and links")

The documents are required in digital form and also in paper form in triplicate.

Duration and costs

Processing time

No general information can be provided on the duration of the procedure. The duration depends on the individual case, the fulfilment of all requirements for a permit and the additional processing time for other specialist departments to be involved in the procedure.

Fees and charges

depending on the withdrawal volume, an additional annual water withdrawal fee ("water cent") may be payable

Legal basis

§§ Sections 8, 10, 15, 49 of the Federal Water Act (WHG)

Articles 15 and 30 of the Bavarian Water Act (BayWG)

Contact Us

Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht
Landeshauptstadt München

Internet address

Postal address

Landeshauptstadt München
Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht

Bayerstraße 28a
80335 München

Address

Bayerstraße 28a
80335 München

Related services

Water law permit - construction projects in groundwater

If you intervene in the groundwater during a construction project, a permit under water law is required.

Drilling indicator well - heat pump/ cooling system up to 50kW

Drilling for the construction of extraction and absorption wells for groundwater heat pumps or cooling systems must be notified in good time before drilling work begins.

Tree felling - protected landscape areas

If you want to cut down a tree or make other changes to a tree in a landscape conservation area, you must submit an application.

Display for a garden fountain

If you wish to install a well to irrigate your private garden with groundwater, you must give at least one month's notice.

Completion of the replacement planting

If you have felled a tree, a replacement planting may be required as compensation. The completion of this replanting must be reported.

Drilling indicator well - heat pump/ cooling system from 50kW

Drilling for the construction of extraction and absorption wells for groundwater heat pumps or cooling systems must be notified in good time before drilling work begins.

Water law permit - rainwater infiltration in water protection areas

A permit under water law is required for the infiltration of rainwater into the ground in a water protection area.

Advice on the ecological criteria catalogue

If you want to build on a municipal property, you must comply with the ecological criteria catalogue of the City of Munich. We can advise you on this.

Water law permit - geothermal probe/ geothermal collector

A permit under water law is required for the construction of a geothermal system (probe, collector, baskets or similar) with groundwater contact.