Drilling indicator well - heat pump/ cooling system from 50kW
Drilling for the construction of extraction and absorption wells for groundwater heat pumps or cooling systems must be notified in good time before drilling work begins.
Course description
Drilling into quaternary gravel layers and outside of water protection areas must be reported to the responsible authority. In the city of Munich, this is the Department for Climate and Environmental Protection.
The work can be started after a period of one month. The period begins with the receipt of the complete notification documents. The prerequisite is that the competent authority does not prohibit the drilling within this month
Please note
Boreholes that go several metres into the deeper tertiary layers(clay, silt, sand) require a permit under water law in addition to the drilling notification.
A separate permit under water law is required for the operation of the groundwater heat pump or cooling system.
Required documents
The documents should preferably be submitted digitally.
- Completed notification form
- General site plan M 1:25,000 with marking of the location
- Detailed site plan M 1:5,000 or M 1:1,000 with entry of the well locations
Legal basis
§ Section 49 of the Water Resources Act (BayWG)Article 30 of the Bavarian Water Act (BayWG)
Contact Us
Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht
Landeshauptstadt München
Internet address
Postal address
Landeshauptstadt München
Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht
Bayerstraße 28a
80335 München
Address
Bayerstraße 28a
80335 München